Current Capital Improvement Program Projects

Print
Press Enter to show all options, press Tab go to next option

Current Roadway/Bridge Projects:

Upcoming Roadway/Bridge Projects:

Replacement of Bohemia Church Road Culverts
This project is the replacement of three existing deteriorated corrugated metal pipe culverts with new reinforced concrete pipes with concrete headwalls and wingwalls, and associated roadway work. Two culverts are located between Christopher Road and Worsell Manor Road, and the third is located approximately 1000 feet west of the intersection with Church Road. The project will be advertised in February/March 2018 with construction beginning in June 2018. Two different detours will be required during construction and the first will implemented in August 2018.
Project Manager: Mike Evans
Bohemia Church Road Public Meeting Information

Mechanics Valley Road Bridge over CSX Railroad, Bridge No. CE0042
This project is the replacement of an existing prestressed concrete bridge on reinforced concrete foundations over CSX railroad with a new bridge and approach roadway that will safely meet the current and future roadway needs. The project is in the preliminary design phase that will position a new bridge to the west of the existing bridge. Identified as a Federal Funding Project, the County must complete the design in phases and receive Federal approval before moving to semi-final design. Pending future approval and appropriation of funds construction is anticipated to be in Fiscal Year 2020.
Project Manager: John Fabian
Mechanics Valley Road Bridge CE0042 Public Meeting Information

Lums Road Street Improvements
This project involves the widening of Lums Road between Bouchelle Road and approximately 500 feet west of Plummer Road near the bridge over Northeast Creek. The project is currently in the Property acquisition phase and contact with property owners is set for late 2018. The project is seeking construction funds in Fiscal Year 2019 and if approved, the project will be advertised for construction in June/July 2019 and construction complete by end of 2020.
Project Manager: John Fabian
Lums Road Street Improvement Public Meeting Information 

Oldfield Point Road Improvements
The project limits are from Old Chestnut Road south to Breon Lane and will include widening roadway, improving horizontal and vertical roadway alignments, drainage improvements, replacement of culverts at Jones Creek and smaller culverts at several other locations. The project is currently in final design and permitting. Property acquisition phase is underway and the County's consultant Property Specialists, JMT, has started at the south end of the project limits and will be moving north in three phases. Presently, JMT is contacting affected property owners between Tomax Lane to Rockmere Lane. 
Project Manager: John Fabian
Old Field Point Road Improvements Public Meeting Information - March 2013
Old Field Point Road Improvement Update

 

Current Solid Waste Projects:

Central Landfill Horizontal Expansion
As is typical with landfill facilities, existing disposal capacity is a finite resource and planning for ongoing and increasing disposal demand is required in order to maintain uninterrupted operations to serve the citizens of Cecil County.  Current disposal activity occurs within Cell 4 which has a remaining capacity on the order of 8 to 12 years.  The horizontal expansion project consists of the design and permitting of 80+ acres comprising six (6) new disposal cells which will subsequently be constructed in phases.  The proposed expansion will provide ongoing service for many decades with a total disposal capacity of approximately 16.6 million cubic yards.  Currently, the County has received the required permits for expansion with the 5-phase regulatory permitting process, MDE will issue separate permits for each new cell.
Project Manager:  Craig Marker

Current Waste Water Projects:

Elkton West Sanitary Sewer Subdistrict Phase 1- Marley Road Sewer Extension
Marley Road Sewer Extension is the first phase of construction for the Elkton West Sanitary Sewer Subdistrict.  The project will extend gravity sewer from an existing tie-in location located at the entrance of AUI Power along the south side of Route 40 approximately 1000’ east of the Marley Road intersection.  Gravity sewer will also be extended approximately 700’ up Marley Road north of Route 40.

The project includes construction of approximately 540 LF of 8” gravity sewer piping and 2,620 LF of 12” gravity sewer piping.  The project includes but is not limited to installation of sewer piping, manhole(s), sanitary sewer house connections up to the right of way line, a jack and bore under Route 40, paving restoration, and maintenance of traffic.
Project Manager:  Craig Marker

Harbour View Wastewater Treatment Plant
This project will replace a wastewater treatment plant (WWTP) that has exceeded its useful life. It consist of constructing a new WWTP outside of the 100-year floodplain and will incorporate a membrane bioreactor package plant that will treat wastewater to Enhanced Nutrient Removal levels. The WWTP is permitted for 65,000 gpd. It will not serve new development but only the existing houses that are already on sewer and those parcels in the Harbour View development shown as S-1 on the County's Master Water and Sewer plan. The project will improve water quality, eliminate potential public health concerns and help meet the nutrient Total Maximum Daily Load for the Elk River.
Project Manager: Jonathan Pohlman

Port Deposit Wastewater Treatment Plant and Pump Station/Force main/Gravity Effluent Outfall
The project will construct a new wastewater treatment plant (WWTP), sewage pumping station, force main and gravity effluent outfall. The WWTP will be capable of treating wastewater to Enhanced Nutrient Removal (ENR) levels and will replace the existing, fifty-year old WWTP. The new plant will be constructed out of the Susquehanna Flood zone at a higher elevation to eliminate the risk of failure during high water releases from the Conowingo Dam.

It will be designed to be expandable to treat wastewater from future development at the Bainbridge site and for taking mobile home parks off of failed or failing onsite treatment systems.

The new plant will be constructed in phases. The first phase will have a capacity of 150,000 gpd (i.e., the current permitted limit). It will be designed to facilitate expansion up to 900,000 gpd as future need requires.
Project Manager: Jonathan Pohlman

Free viewers are required for some of the attached documents.
They can be downloaded by clicking on the icons below.

Acrobat Reader Flash Player Windows Media Player Microsoft Silverlight Word Viewer Excel Viewer PowerPoint Viewer